- Revisions to Conceptual Master Plan completed by JFDS (Joseph Furr Design Studio)
- Three Park/Skate Park Design Firms were interviewed by a Selection Committee for Design Development and Construction Document Services -- June 11, 2007
- BREC Commission selected SITE Design Group, Inc. for Design Development and Construction Document Services -- June 26, 2007
- Public Planning & Design Workshop --Held Tuesday, August 21st from PM
- #2 Public Planning & Design Workshop -- Held Saturday, September 22, 2007 from 10am - 12 noon.
- Construction Bid was awarded to Charles Carter Construction on February 26, 2009.
- Construction Underway as of April 2009.
- The Recreation Center, Ball Fields and Olympia Stadium will remain Open to the Public during construction. The parking lots will open and close at various times depending on sequencing of new construction.
- Grand Re-Opening and Ribbon Cutting to celebrate the renovation of BREC's Perkins Road Community Park to be held on Oct. 16, 2010 at 10 a.m.
|
|
|