Park Improvements

N. 14th Street Park


(Click to enlarge)

New Features in Current Project Improvements:

  • New/repaired windows & doors
  • Possible Mural
  • New Paint
  • New Ornamental Fencing
  • Reconfigured Basketball Court

Project Updates

  • August 2018 - Design in development
  • December 2018 - Permitting underway
  • January 2019 - Scheduling lead abatement. Working on permit for major work.

Estimated Budget for Current Improvements: $130,000

Estimated Completion for Current Improvements: Spring 2019