Park Improvements

Church Street Park


(Click to enlarge)

New Features in Current Project Improvements:

  • Repaired Flood damage
  • NEW multi-purpose room with kitchenette & storage space
  • NEW restrooms
  • NEW offices
  • NEW heat & air conditioning in all rooms & gym
  • NEW basketball goal systems
  • IMPROVED entry

Project Updates

  • July 2018 - Project out for bid; Bid awarded to BDS Construction
  • August 2018 - Permitting
  • October 2018 - Notice to proceed issued to BDS Construction
  • November 2018 - Construction underway
  • December 2018 - Demolition Phase
  • January 2019 - Drainage, building slab addition, and utilities. Pending dry weather.
  • March 2019 - 15% complete, Foundation dug, Concrete pour, plumbing and treatments next, Electrical Utilities
  • April 2019 - 40% complete, Framing and concrete going up

Estimated Budget/Construction Costs for Current Improvements: $1,200,000

Estimated Completion for Current Improvements: Fall 2019