Park Improvements

Fiesta Park


(Click to enlarge)

New Features in Current Project Improvements:

  • New walks
  • New pavilion
  • New benches & picnic tables
  • New outdoor fitness equipment

Project Updates

  • March 2018 - Park identified for improvements; master plan design underway
  • April 2018 - Constuction underway
  • June 2018 - Walking path 75% done; pavilion under construction
  • July 2018 - fitness equipment ordered
  • August 2018 - Fitness Equipment being installed
  • October 2018 - Preparation for sod
  • December 2018 - Final sod added; project complete

Estimated Budget/Construction Cost: $84,500

Completion for Current Improvements: December 2018