Project Updates:

  • April 2016 - Bid issued
  • June 2016 - Notice to Proceed issued to Wharton-Smith, Inc.
  • July 2016 - Groundbreaking ceremony held
  • August 2017 - Construction experiencing delays due to weather.
  • Setpember 2017 - Construction estimate at 85% compleition
  • October 2017 - Contractor wrapping up scope; permitting, etc. next.
  • January 2018 - Flood repairs underway for new construction
  • November 2018 - Bid for flood repairs to existing structure awareded to ANR Construction
  • January 2019 - Mold abatement underway. Flood repair immediately to follow.
  • February 2019 - Remediation complete; Repair to existing structure underway
  • March 2019 - 20% Complete, Remediation complete; repair to existing structure underway
  • April 2019 - 40% Complete, Brick exterior underway
  • June 2019 - 65% Complete, Working in gym / HVAC System
  • July 2019 - 80% Complete
  • September 2019 - 95% Complete
  • October 2019 - 99% Complete
  • November 2019 - 99% Complete, Finalizing construction

Estimated Completion for Current Improvements: Spring 2020