Park Improvements

Warren O. Watson Park


(Click to enlarge)

New Features in Current Project Improvements:

  • New Playground
  • Improved & Expanded Walking path

Project Updates

  • July 2018 - Park identified for improvements
  • August 2018 - Online public input survey underway
  • December 2018 - Design complete; construction to start early 2019
  • January 2019 - Construction underway
  • March 2019 - 90% Complete - colorful playground installed, some site work still left
  • April 2019 - 99% Complete - Finish Paint and clean up; In punch list - grass seeding

Estimated Budget/Construction Cost for Current Improvements: $71,500

Estimated Completion Date: Spring 2019

Site by Covalent Logic