Park Improvements

Milton J. Womack Park


(Click to enlarge)

New Features in Current Project Improvements:

  • New lighted multi-use fields
  • New bleacher
  • New restrooms
  • New walks & paved parking lot

Project Updates

  • May 2017 - Park identified for improvements; planning phase initiated.
  • August 2017 - Design consultant starting on schematic design. Public input in September
  • March 2017 - Bid opened
  • May 2017 - Notice to Proceed issued to Industrial Enterprises Inc
  • May 2018 - Substantially complete; working on grass grow
  • June 2018 - equipment ordered; grand opening scheduled for August
  • July 2018 - Permitting in progress
  • August 2018 - Grand opening prep

Estimated Budget for Current Improvements: $300,000

Estimated Completion for Current Improvements: September 2018