Park Improvements

Woodlawn Acres Park


(Click to enlarge)

New Features in Current Project Improvements:

  • NEW playground
  • NEW partial walking loop
  • NEW practice cricket pitch
  • NEW cricket pitch & Field
  • NEW picnic shelter / pavilion

Project Updates

  • August 2017 - Wetlands determination required; plans will be adjusted based on result
  • July 2018 - Public input survey being developed
  • September 2018 - Public input survey conducted
  • December 2018 - in design
  • February 2019 - project out to bid
  • March 2019 - Bid awarded, Contracting underway
  • June 2019 - Construction underway
  • July 2019 - 20% Complete

Estimated Budget/Construction Costs for Current Improvements: $132,620

Estimated Completion for Current Improvements: Spring 2020