Clifford T. Seymour Park - Improvements
New Features in Current Project Improvements:
- Renovate basketball court with new fencing, backboards, goals, posts, and court surfacing
- New paved handicap-accessible parking and sidewalks
- New picnic pavilion and grilling area
- New park benches, accessible picnic tables, and drinking fountain
- New park signage
Project Updates
- January 2025: Planning and design
- January 2025: Public input survey open to the public until January 31
- March 2026: Construction drawings complete
- April 2026: Construction underway on park site improvements
- June 2026: The new entry park sign has been completed
Estimated Completion for Current Improvements: November 2026