Clifford T. Seymour Park - Improvements

Visit Facility Page

 

New Features in Current Project Improvements:

  • Renovate basketball court with new fencing, backboards, goals, posts, and court surfacing
  • New paved handicap-accessible parking and sidewalks
  • New picnic pavilion and grilling area
  • New park benches, accessible picnic tables, and drinking fountain
  • New park signage

Project Updates

  • January 2025: Planning and design
  • January 2025: Public input survey open to the public until January 31
  • March 2026: Construction drawings complete
  • April 2026: Construction underway on park site improvements
  • June 2026: The new entry park sign has been completed

Estimated Completion for Current Improvements: November 2026