Park Improvements

Bluebonnet Swamp Nature Center

Visit Facility Page

Bluebonnet Swamp Nature Center Porte Cochere Render
(Click to enlarge)

New Features in Current Project Improvements:

  • New Education Building - Porte Cochere

Project Updates

  • September 2020 - Project in design, construction to begin spring 2021
  • February 2021 - Design development stage, going over designs from consultant, construction to begin summer 2021
  • June 2021 - Project in bidding stage, in process of sending project out for quotes
  • November 2021 - Received bid results and working on recommended contractors.
  • February 2022 - 5% Complete; contractor is pouring concrete footings.
  • May 2022 - 65% Complete; roof panels to be installed
  • June 2022 - 100% Complete; project has been completed and porte cochere is ready to be used by school buses and the public.

Completion for Current Improvements: Summer 2022

Previous Improvements

Bluebonnet Swamp 2017 Park Improvements

Features:

  • New connector paths
  • New employee access drive
  • New connector drive
  • Newly paved asphalt drive
  • Reinforced grass parking

Completed: December 2018
Click to view project timeline