PRESCRIBED BURN NOTICE: Prescribed or controlled burn to take place at Howell Community Park tentatively starting Thursday, January 19, 2023 depending on the weather Please do not report incidents of smoke or fire in Howell Community Park. The burn has been approved by the local fire department. Click here to learn more about prescribed burns

Park Improvements

Brookfield Avenue Park

Visit Facility Page


(Click to enlarge)

New Features in Current Project Improvements:

  • New Playground Equipment
  • New Walking Loop

Project Updates

  • May 2019 - Public input survey being developed
  • June 2019 - Public input survey conducted
  • July 2019 - In design
  • November 2019 - Construction Underway
  • January 2020 - Construction 20% complete
  • March 2020 - 95% Complete, Playground equipment and walking loop installed. Crews finalizing improvements.
  • June 2020 - 98% Complete
  • September 2020 - 99% Complete, need to install benches and grass seed
  • February 2021 - 100% complete