City-Brooks Community Park - Improvements

Visit Facility Page

Features in Current Project Improvements:

  • IMPROVED Drainage, re-grading, and turf in large dog park
  • IMPROVEMENTS to dog wash stations

Project Updates

  • July 2021 - Posted upcoming park closure, start date for construction TBD.
  • November 2021 - Landscape being completed, the grass growing period has been completed and grass is established in the ground. Wind screens have been placed by the dog wash stations to prevent overspray. To be reopened to the public next month
  • December 2021 - Re-grassing project completed. Dog Park is open to the public.

 

Previous Improvements

Features

  • NEW Safety Surfacing
  • IMPROVED Drainage

COMPLETED JUNE 2021 (Click to view project timeline)

Project Updates:

  • SEPTEMBER 2020 - Project in planning
  • FEBRUARY 2021 - 90% Complete, EWF to be installed and concrete to be poured.
  • APRIL 2021 - 98% Complete, punch list items to be completed, playground is open to the public
  • JUNE 2021 - 100% Complete, Project Completed

 

Features

  • EXPANDED Large Dog Park Area
  • NEW Small Dog Park Area
  • IMPROVED Drainage

COMPLETED DECEMBER 2020 (Click to view project timeline)

Project Updates:

  • SEPTEMBER 2019 - Out to Bid
  • NOVEMBER 2019 - Awarded & approved by Commission, in contracting
  • DECEMBER 2019 - Groundbreaking scheduled
  • JANUARY 2020 - 1% Complete, Under Construction
  • FEBRUARY 2020 - 15% complete
  • APRIL 2020 - 25% Complete
  • JUNE 2020 - 55% Complete; majority of fence posts are up, concrete curbing for active dog play areas is nearly complete, bench pads are poured, and decomposed granite in active dog areas being placed.
  • SEPTEMBER 2020 - 85% Complete; plaza pavers complete, continuing fence construction
  • NOVEMBER 2020 - 90% Complete; construction continuing
  • DECEMBER 2020 - Project complete; soft opening held

 

CITY-BROOKS croquet court rendering layout

Features

  • NEW Tournament Level Croquet Court
  • NEW pavilion
  • NEW storage shed
  • IMPROVED paving

COMPLETED JANUARY 2019 (Click to view project timeline)

Project Updates:

  • JUNE 2018 - Construction of croquet pitch, trailhead, and event space is well underway
  • JANUARY 2019 - Croquet court construction complete