Features:
- Expanded Large Dog Park Area
- New Small Dog Park Area
- improved Drainage
Completed: December 2020 Click to view project timeline
Project Updates
- September 2019 - Out to Bid
- November 2019 - Awarded & approved by Commission, in contracting
- December 2019 - Groundbreaking scheduled
- January 2020 - 1% Complete, Under Construction
- February 2020 - 15% complete
- April 2020 - 25% Complete
- June 2020 - 55% Complete; majority of fence posts are up, concrete curbing for active dog play areas is nearly complete, bench pads are poured, and decomposed granite in active dog areas being placed.
- September 2020 - 85% Complete; plaza pavers complete, continuing fence construction
- November 2020 - 90% Complete; construction continuing
- December 2020 - Project complete; soft opening held
|