New Features in Current Project Improvements:

  • New Timber Bridges: All bridge replacements will be compliant with the Americans with Disabilities Act (ADA)

Project Updates

  • July 2026: Bridge demolition underway

Estimated Completion TBD


Previous Improvements

House Renovation, Completed 2022 (Click to view project)

Features

  • Renovate historic bungalow

Project Updates

  • September 2020 - Project completed design phase; project to go out to bid soon
  • November 2020 - Project in bidding
  • February 2021 - 15% Complete, project underway and roof completed
  • March 2021 - 20% Complete, construction continuing
  • April 2021 - 40% Complete, abatement completed, construction continuing
  • June 2021 - 80% Complete, renovation construction continuing
  • July 2021 - 90% Complete, renovation construction continuing.
  • August 2021 - 95% Complete, renovation construction continuing.
  • November 2021 - 98% Complete, project is substantially completed
  • May 2022-  Complete

Historical Building Abatement, Completed 2020 (Click to view project)

Features

  • House abatement prior to restoration construction

Project Updates

  • December 2018 - Project in design
  • January 2020 - Abatement advertised
  • September 2020 - 100% complete, lead-containing paint stabilization complete