Park Improvements

Cohn Arboretum

Visit Facility Page


(Click to enlarge)

New Features in Current Project Improvements:

  • Renovated bungalow

Project Updates

  • September 2020 - Project completed design phase, project to go out to bid soon
  • November 2020 - Project in bidding
  • February 2021 - 15% Complete, project underway and roof completed
  • March 2021 - 20% Complete, construction continuing
  • April 2021 - 40% Complete, abatement completed, construction continuing
  • June 2021 - 80% Complete, renovation construction continuing
  • July 2021 - 90% Complete, renovation construction continuing.
  • August 2021 - 95% Complete, renovation construction continuing.

Estimated Completion Date: Fall 2021

Previous Improvements

Features:

  • Renovated historical building (including abatement)

Completed: Late Summer 2020
Click to view project timeline