Park Improvements
Forest Community Park
New Features in Current Project Improvements:
- new play area
- new lobby/reception area
- new meeting rooms
- new multi-purpose room
- new restrooms
- new storage space
- new heat & air conditioning
- resurfaced gym floor
Project Updates:
- April 2016 - Bid issued
- June 2016 - Notice to Proceed issued to Wharton-Smith, Inc.
- July 2016 - Groundbreaking ceremony held
- August 2017 - Construction experiencing delays due to weather.
- Setpember 2017 - Construction estimate at 85% compleition
- October 2017 - Contractor wrapping up scope; permitting, etc. next.
- January 2018 - Flood repairs underway for new construction
- November 2018 - Bid for flood repairs to existing structure awareded to ANR Construction
- January 2019 - Mold abatement underway. Flood repair immediately to follow.
- February 2019 - Remediation complete; Repair to existing structure underway
- March 2019 - 20% Complete, Remediation complete; repair to existing structure underway
- April 2019 - 40% Complete, Brick exterior underway
- June 2019 - 65% Complete, Working in gym / HVAC System
- July 2019 - 80% Complete
- September 2019 - 95% Complete
- October 2019 - 99% Complete
- December 2019 - 99% Complete, Finalizing construction
- February 2020 - Construction Complete
Completion Date for Listed Improvements: Spring 2020