Park Improvements

Frenchtown Road Conservation Area

Visit Facility Page


(Click to enlarge)

New Features in Current Project Improvements:

  • New Education Building

Project Updates

  • December 2018 - Project in design
  • February 2019 - bid preparations; adjustments made for fire code specifications
  • July 2019 - Public input meetings conducted; public input survey conducted
  • October 2019 - Permitting
  • September 2020 - In contracting
  • November 2020 - In pre-construction phase, Construction to begin soon

Estimated Completion for Current Improvements: Late Fall 2021