Jackson Community Park
Visit Facility Page

(Click to enlarge)
Features in Current Project Improvements:
- New Recreation Center
- New Playground
- New Shade Structures
- New Green space & lighting
Project Updates
- October 2020 - Construction underway
- November 2020 - 5% Complete; Construction underway
- January 2021 - 10% Complete; Construction underway - foundation for recreation center to be poured shortly
Estimated Completion for Current Improvements: Late 2021
Previous Improvements
Jackson Community Park underwent a master planning process for park renovations. In 2012, two public planning meetings were held at Jackson Park. A conceptual master plan was presented to the public showing potential site enhancements throughout the park and to gain insight for the preferred location of a new splash pad. In 2015, construction was completed for a new splash pad with connector pathways and new outdoor restrooms.
 (Click to enlarge)
|
Features:
- New parking
- New vehicle drop off
- New site lighting
- Improved drainage
- New walking trail
- New outdoor fitness equipment
Completed: December 2020 Click to view project timeline
Project Updates
- November 2017 - Public input survey conducted
- July 2018 - Groundbreaking scheduled for the fall.
- August 2019 - Shade sails added to splashpad benches
- December 2018 - Project in design
- February 2019 - Phase 1 out to bid
- March 2019 - Bid awarded, Contracting underway
- April 2019 - Notice to Proceed issued
- June 2019 - 5% Complete, Walk thru, construction under way, removal of trees and installed construction fencing
- July 2019 - 7% Complete, Site drainage work began
- September 2019 - 25% Complete, Sidewalks constuction, completing walking loop
- November 2019 - 50% Complete, Parking lot curb & gutter installed, parking lot asphalt coming soon
- January 2020 - 75% Complete, Parking lot construction in progress
- February 2020 - 80% Complete, Parking lot construction in progress
- June 2020 - 95% Complete; phase 1 wrapping up
- September 2020 - 99% Complete
- November 2020 - 99% complete; Substainally complete, punch list items being addressed
- January 2021 - 100% complete
|