Park Improvements
Santa Maria Golf Course & Park
New Features in Current Project Improvements:
- Remodeled 2nd Floor Back Porch
- Remodeled Restroom
- New Roof
Project Updates
- July 2021 - Project in contracting phase, contracting documents being discussed and scope being finalized
- November 2021 - 1st Phase: Roof Replacement, 2nd Phase: Interior improvements, restroom. Working on scope & budget
- February 2022 - 1st Phase: Roof Replacement - awaiting contracting, 2nd Phase: Interior improvements, restroom - P&E team working with architect to define scope and budget.
- May 2022 - 1st Phase: Roof Replacement - awaiting contracting, 2nd Phase: Interior improvements, restroom - P&E team working with architect to define scope and budget.
Estimated Completion for Current Improvements: TBD
Previous Improvements
Features:
Completed: February 2017 |