Greenwood Community Park - Improvements
CYPRESS BAYOU GREEN INFRASTRUCTURE PROJECT

Cypress Bayou and Greenwood Lake are prominent features within the park's landscape. The lake, typically a thriving recreational hub featuring canoeing and fishing, has suffered in recent years from sedimentation and the spread of invasive water hyacinth. To address these issues BREC is leverging funding from the Office of Community Development's Louisiana Watershed Initiative to help reduce future flood impacts to adjacent neighborhoods. To accomplish this, the lake is being deepened and expanded. Additionally, Cypress Bayou is being widened to improve flow and stability of the channel. The bayou and lake will be greatly improved for recreational activities such as paddling and fishing.
New Features in Current Project Improvements
- DEEPENED and EXPANDED Greenwood Lake
- WIDENED Cypress Bayou flowing into Greenwood Lake
- IMPROVED fishing and paddling opportunities
- NEW walking trails
Project Updates
- July 2025 - Construction begins
- January 2027 - Lake and Cypress Bayou improvements expected to be Complete
LAVEY LANE CONNECTOR ROAD AT GREENWOOD COMMUNITY PARK
New Features in Current Project Improvements
- New Park Entrance Road connecting Lavey Lane to Greenwood Community Park
Project Updates
- July 2026 - Bid Project
- October 2026 - Change in scope of work. The project is now being redesigned.

Previous Improvements
Features
- New pickleball courts (12)
COMPLETED In 2021 (Click to view project timeline)
Project Updates:
- June 2021 - 10% Complete; project underway: demolition of existing tennis courts has started
- August 2021 - 75% Complete, awaiting delivery and installation of pickleball netting
- October 2021 - 100% Complete
Previous Improvements
Features
- NEW rental space
- NEW office
- NEW warming kitchen
COMPLETED JANUARY 2021 (Click to view project timeline)
Project Updates:
- APRIL 2019 - Bid approved by Commission
- JUNE 2019 - Contract finalized, Permits to be finalized, Notice to proceed soon
- JULY 2019 - Notice to proceed issued
- NOVEMBER 2019 - November 2019 - 20% Complete
- JANUARY 2020 - 40% Complete, Building addition underway
- FEBRUARY 2020 - 45% Complete, Walls going up, putting up metal studs, roof going up
- APRIL 2020 - 65% Complete, Interior work beginning. Work slowed by Covid-19
- JUNE 2020 - 80% Complete; HVAC work currently underway
- SEPTEMBER 2020 - 95% Complete; Construction nearly complete, to be completed later in September
- OCTOBER 2020 - 99% Complete; substantially complete, punch list items being addressed
- JANUARY 2021 - 100% Complete; building complete and site work underway