Features:
- NEW rental space
- NEW office
- NEW warming kitchen
Completed: January 2021 Click to view project timeline
Project Updates
- April 2019 - Bid approved by Commission
- June 2019 - Contract finalized, Permits to be finalized, Notice to proceed soon
- July 2019 - Noticed to proceed issued
- November 2019 - November 2019 - 20% complete
- January 2020 - 40% Complete, Building addition underway
- February 2020 - 45% Complete, Walls going up, putting up metal studs, roof going up
- April 2020 - 65% complete, Interior work beginning. Work slowed by Covid-19
- June 2020 - 80% complete; HVAC work currently underway
- September 2020 - 95% complete; Construction nearly complete, to be completed later in September
- October 2020 - 99% complete; Substainally complete, punch list items being addressed
- January 2021 - 100% Complete, builidng complete and site work underway
|